Info |
---|
Note that this page is specific to SPARSE Lookups. Regular Lookup stages do not need any special considerations for MettleCI Unit Testing. |
Sparse Lookup Stage ('Explicit' test method)
When building DataStage jobs using the Lookup stage, performing a Sparse or Normal lookup is as simple as changing the lookup type of the reference Database stage. When a DataStage job featuring a sparse Lookup is compiled to OSH and executed, however, the Lookup stage is not used to perform the sparse lookup. Instead, DataStage replaces the Lookup stage with the Database operator which is responsible for reading input rows, looking up values from the database and producing output records. It is for this reason that all Database log messages in the DataStage Director are attributed to the Lookup stage and why the Database stage never appears in the Monitor of the DataStage Director.
To Unit Test job designs using Sparse Lookup stages the sparse lookup functionality needs to be explicitly replaced with user-supplied Unit Test data:
The most explicit way to configure Unit Testing to replace a Sparse Lookup with Test data is by adding the input link to the then
(expected outputs) clause of the Unit Test Spec and the output link to the given
(supplied inputs) clause of the Job’s Unit Test Specification.
The CSV file specified in the
then
clause contains the data that will be be compared to the data flow of records arriving at the input of the Sparse Lookup stage. The data should describe what records are expected to be used to provide the sparse lookup’s key columns.The CSV file specified in the
given
clause contains the data that will be become the data flow of records from the output of the Sparse Lookup stage. The data should simulate what would be produced by the real Sparse Lookup Stage if it had actually processed the Unit Test input records against the real database reference source, however they don't have to.
Code Block |
---|
given: - stage: SparseLookup link: Output path: SparseLookup-Output.csv when: ... then: - stage: SparseLookup link: Input path: SparseLookup-Input.csv |
Sparse Lookup Stage ('Replace' method)
MettleCI Unit Test Harness version 1.1-379
, MettleCI and later provides a convenient alternative which replaces capability which uses the new Unit Test Specification spareseLookup
clause to replace the entire Sparse Lookup stage with Test Data while only requiring the user to supply Test Data for the reference link:
Code Block |
---|
given: - sparseLookup: SparseLookup path: Database-Reference.csv key: - KEY_COLUMN_1 - KEY_COLUMN_2 ... |
In this mode the Sparse Lookup stage is replaced entirely with a Unit Test version of the sparse lookup which uses the specified Test Data as the lookup data. It is provided as a convenient alternative to explicitly replacing Sparse Lookup stage input /and output links, allowing the remaining logic in the job to be tested , it does while not actually test testing the behaviour of DataStage’s Sparse Lookup stage itself.
From Workbench version 1.0-1483, When generating Unit Tests generated from Job designs containing Sparse Lookups, MettleCI Workbench version 1.0-1483
and later will automatically apply this Unit Test pattern and generate test specifications which replace Sparse Lookup stages entirely.
Note |
---|
Known Limitations The use of replacing Replacing the Sparse Lookup stage with a Unit Test version of the sparse lookup comes with some limitations that DataStage developers should keep in mind. Where these limitations are considered to be unacceptable, it is recommended that the explicit method for replacing Sparse Lookups be applied.
|
Where you consider these limitations unacceptable you can revert to the original (explicit) method for replacing Sparse Lookups. |
A pragmatic approach for Multiple Sparse Lookups
For jobs where the vast majority of job logic is implemented using Sparse Lookup stages, replacing all lookups with Unit Test data would result in little-to-no DataStage logic being tested (as illustrated below).
For this the type of Job design , an show above, a traditional explicit testing approach would necessitate the developer providing 8 sets of test data! An alternative testing approach is to leave the Sparse Lookup Lookups in place and replace only the input and output stages with Unit Test data. A live Database connection will be required during testing but the when
clause can be used to set job parameters that dictate database connection settings.
Note |
---|
Technically this is an Integration Test, not a Unit Test: The Unit Test Harness does not provide any functionality for populating database reference tables with Unit Test data prior to test execution, users are responsible for managing Integration Test setup and tear down through governance and/or CI/CD pipeline customisation. |
Code Block | ||
---|---|---|
| ||
given: - stage: Source link: Input path: Source-Output.csv when: parameters: DbName: MyUnitTestDb DbUser: MyUnitTestUser DbPass: {iisenc}dKANDae233DJIQeiidm== then: - stage: Taret link: Output path: Target-Output.csv |