Purpose
Run one or more MettleCI Unit Tests against one or more DataStage jobs.
The -reports
option is used to specify the directory into which the JUnit XML files produced by this command will be placed. Each job tested will produce a separate XML file named after the Job (e.g. Job MY_JOB_ABC
will produce a JUnit file named MY_JOB_ABC.xml
)
The -ignore-test-failures
option will prevent a failing Unit Test from being interpreted as a command failure by your build system, and consequently halting your CI/CD pipeline.
See Repeatable DataStage Project Deployments for more details on how the -project-cache
parameter is used to implement incremental tests. For more information on using the -project-cache
parameter see our detailed explanation.
Syntax
Example
C:\> mettleci unittest test ^
-domain test1-svcs.datamigrators.io:59445 ^
-server test1-engn.datamigrators.io ^
-username isadmin ^
-password my_password ^
-project my_project ^
-specs unittest ^
-reports unittest_reports ^
-project-cache "C:\MettleCI\cache\test1-engn.datamigrators.io\my_project"
MettleCI Command Line (build 128)
(C) 2018-2022 Data Migrators Pty Ltd
Loading Unit Test Specifications from 'unittest'
Reading test1-engn.datamigrators.io/my_project
Attempting to identify changes with 1 working threads.
Inspecting DataStage assets for changes...
* Check test1-engn.datamigrators.io/my_project/Jobs/Transform/TR_ORDERS.pjb - COMPLETED
Change identification complete
Executing Tests with 4 concurrent jobs...
* Test TR_ORDERS/TR_ORDERS - SKIPPED
Updating incremental state...
Attempting to identify last change with 1 working threads.
Inspecting DataStage assets for last change...
* Check test1-engn.datamigrators.io/my_project/Jobs/Transform/TR_ORDERS.pjb - COMPLETED
Last change identification complete
Test execution completed successfully.